LAND ACQUISITION PROCEDURES IN TURKEY

The new Expropriation Law and the procedures by which it is implemented differ in some important ways from the previous ones. This section will deal with: (i) land acquisition and valuation procedures; (ii) organisational and implementation issues and gaps; (iii) institutional responsibilities, and (iv) approaches that the Project will take to minimise issues that have arisen or may arise during land acquisition implementation. In addition, organisational and institutional issues will be discussed.

1.2  Land Acquisition Procedures


The new Expropriation Law and the procedures by which it is implemented differ in some important ways from the previous ones.  This section will deal with: (i) land acquisition and valuation procedures; (ii) organisational and implementation issues and gaps; (iii) institutional responsibilities, and (iv) approaches that the Project will take to minimise issues that have arisen or may arise during land acquisition implementation.  In addition, organisational and institutional issues will be discussed.

 
1.2.1  Preliminary Land Acquisition Procedures


This section describes the preliminary procedures that the Authority has undertaken (or will undertake) before land acquisition, resettlement and compensation.  The procedures can be broadly grouped into two phases: those during route selection and those post route selection.

Land must be acquired and made available for the Project before construction can begin. No construction can take place unless the valuation is completed, certified attempts are made to negotiate the transfer of ownership or usage rights from the private owners, and full payment is made to the accounts of owners.

Figure 1.1 illustrates the key steps that are necessary before the land acquisition can begin with notification to the landowner of the intended expropriation.  These key steps are carried out during and after siting, route selection and route narrowing.

 
1.2.1.1   Overview of Siting and Route Selection
 

Pipeline route selection is the process of defining an optimised connection between two or more points to be linked with each other via a pipeline transportation system. The route optimisation is performed as an iterative process that weighs and balances several different influences that are encountered on a route, causing either deviations of the initial line or the need for the implementation of specific construction or design methods, or both.
 

Figure 1.1: Land Acquisiti...